Phase I of Scott Hill Park & Sports Complex is 75% complete. The small, covered shelter and maintenance building with restrooms are up, the walking trail in Phase l has been paved. Work has begun on the entrance road and Phase l parking lots.

Construction Phases

Click to enlarge.

Men Working

Construction Phases

Phase 1:

  • Entrance
  • Trail head restroom
  • Maintenance building/restrooms
  • Parking lot #1
  • Tot toys playground #1
  • Covered shelter – 16’x 16′
  • 1/3 of paved walking trail
  • Multi-use field (natural) soccer & softball
  • Covered event shelter – 40’x 30′
  • 1/3 Landscaping

Phase 2:

  • Parking lot #2
  • 1/3 Paved walking trail
  • 3 Artificial turf soccer fields
  • Restroom Building #1
  • 1/3 Landscaping

Phase 3:

  • 2 Baseball artificial turf fields
  • 2 Softball artificial turf fields
  • Two story concession stand/restrooms
  • Tot toys playground #2
  • Final 1/3 of paved walking trail
  • Batting cages
  • Bull pens
  • Parking lot #3
  • Donor monument
  • Large covered shelter (100’x 60′) with kitchen and storage
  • Restroom building #2
  • Roadway & sidewalk to Meriwether subdivision
  • Final 1/3 landscaping